LCA Site Projects Division was recently awarded the contract for the electrical installation associated with the installation of a new Long Welded Rail processing plant. Successfully completed over a 12 week period LCA Site projects supplied a site based labour force peaking at a total 65 site electrical installation personnel in addition to a site based management team. A total of 20,000 man hours were worked on this project installing over 2,000 metres of new cable containment and over 48,000 metres of new cable.